Route 4 South (NY Route 43 to Valley View Boulevard)
Construction Start: March 29, 2021
Stage 1: March 29, 2021– Bloomingrove Drive westbound approach to Route 4 will be closed with a signed detour in place, shoulder construction will be occurring on Route 4
Stage 2: May 2021
Construction End: July 2021
Route 4 and Winter Street Intersection
Construction Start: September 2021
Stage 1: September 2021
Stage 2: October 2021
Construction End: November 2021
Route 4 and Williams Road Roundabout
Construction Start: March 29, 2021
Stage 1: March 29, 2021
Stage 2A: July 2021
Stage 2B: September 2021
Stage 3: September 2021
Stage 4: Mid-September 2021
Stage 5: Late September 2021 (Night Work)
Construction End: November 2021