Construction Schedule

Route 4 South (NY Route 43 to Valley View Boulevard) 

Construction Start: March 29, 2021

Stage 1: March 29, 2021– Bloomingrove Drive westbound approach to Route 4 will be closed with a signed detour in place, shoulder construction will be occurring on Route 4

Blooming Grove Drive Detour

Stage 2: May 2021

Construction End: July 2021

Route 4 and Winter Street Intersection

Construction Start: September 2021

Stage 1: September 2021

Stage 2: October 2021

Construction End: November 2021

Route 4 and Williams Road Roundabout

Construction Start: March 29, 2021

Stage 1: March 29, 2021

Stage 2A: July 2021

Stage 2B: September 2021

Stage 3: September 2021

Stage 4: Mid-September 2021

Stage 5: Late September 2021 (Night Work)

Construction End: November 2021